DESERT SANDS
300 MW storage in Riverside, CA · In queue since April 2020 · Proposed COD March 2035
300 MW
Capacity
1
Components
Battery
6y 7m
In Queue
IA Executed
IA Phase
Signed Aug 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
4y 4m
IA → COD
10y 7m
Total Duration
4y 4m
Study Phase
C13
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C13
Project under construction
Typical: 6–18 months
Proposed COD: 2035-03-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
medium confidence at research time
- energy-storage.news/california-utility-signs-ppa-with-nextera-for-eight-hour-energy-storage-project/
- utilitydive.com/news/clean-power-alliance-nextera-energy-long-duration-storage/647249/
- cal-cca.org/clean-power-alliance-board-of-directors-approves-long-duration-storage-project-with-nextera-energy-resources-desert-sands-facility/
- desertcommunityenergy.org/wp-content/uploads/2025/08/R.20-05-003-DCE-June-2024-IRP-Filing-Public-Version-c1-c1.pdf
- sdcommunitypower.org/wp-content/uploads/2020/12/0.-AGENDA.2023.10.26.SDCP_.BoardofDirectors.pdf
- cleanview.co/power-projects/planned/battery-storage-projects/california/1758_storage/desert-sands
Commercial operation date: Only the LBNL proposed COD (2035-03-31) is available. The Cleanview listing says it is expected online in 'March ...', which looks derived from LBNL, and the visible snippets give no independent developer COD. The 2035 date looks late for a project with 2023 PPAs and an executed IA, so it may be a placeholder, but nothing in the sources replaces it.
Developer: LBNL has no developer, so there is nothing to compare. Energy-Storage.News, Utility Dive, and the CPA press release all name NextEra Energy Resources as owner of the Desert Sands Energy Storage facility. A DCE filing refers to a project entity, 'Desert Sands Energy Storage II, ...' (name truncated), but it is not the LBNL filing entity.
Status: LBNL shows the project as active with an executed IA, and the 2023-2025 PPA and regulatory coverage shows the project is still being pursued. No source indicates withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The DESERT SANDS project is a proposed 300 MW battery storage project located in Riverside County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1758, with a queue entry date of April 15, 2020. The proposed commercial operation date is March 31, 2035. The project's interconnection status is currently in the System Impact Study phase. Southern California Edison (SCE) is the utility.
The DESERT SANDS project has been featured in recent news coverage related to deals.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Devers Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GARNET_7_N006
- POI Substation
- Devers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesBattery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
DESERT SANDS
Data-driven briefing on DESERT SANDS — fleet, generation, financial, and news signals.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.