SUNRISE BUTTE
150 MW hybrid in Imperial, CA · In queue since April 2019 · Proposed COD January 2027
150 MW
Capacity
1
Components
Battery
7y 7m
In Queue
IA Executed
IA Phase
Signed Oct 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5y 6m
IA → COD
2y 3m
Total Duration
5y 6m
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C12
Project under construction
Typical: 18–30 months
Proposed COD: 2027-01-18
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per CAISO queue
caiso.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-1667
- cleanview.co/power-projects/planned/solar-farms/california/1667_photovoltaic/sunrise-butte
- cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/summer-2021-reliability/tracking-energy-development/260106-sdge-response-to-president-reynolds-251121-letter.pdf
- caiso.com/documents/publicqueuereport.xlsx
Commercial operation date: LBNL queue shows proposed COD of 2027-01-18. One search result (Cleanview battery page) mentions November 2029, but this appears to be a data error or separate storage component estimate. No press releases or developer announcements found to contradict the LBNL date with higher confidence.
Developer: No developer identified in LBNL snapshot. Search results contain only queue-tracking databases and regulatory filings with no developer attribution. No press releases, corporate announcements, or ownership information found.
Status: LBNL shows 'active' status with IA executed on 2024-10-08. CPUC tracking document from January 2026 lists project in active queue. No withdrawal or suspension signals found.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SUNRISE BUTTE project is a proposed 150 MW hybrid solar and battery energy storage project located in Imperial County, California. Interconnecting to the Imperial Valley Substation at 230 kV, the project consists of solar generation paired with a 150 MW battery energy storage system.
The project is listed in the CAISO interconnection queue as queue ID CAISO-1667, with an entry date of April 15, 2019. The proposed commercial operation date is November 18, 2029, and the interconnection agreement has been executed. The project is actively listed in the queue and is within the service territory of SDGE.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Imperial
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Imperial Valley Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WESCAN_7_N002
- POI Substation
- Imperial Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.