BONANZA SOLAR
600 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD September 2028
600 MW
Capacity
2
Components
Solar + Battery
7y 7m
In Queue
IA Executed
IA Phase
Signed Nov 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 7m
IA → COD
6y 10m
Total Duration
2y 7m
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C12
Project under construction
Typical: 18–30 months
Proposed COD: 2028-09-30
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
EDF states Bonanza Solar+Storage (up to 300 MW solar plus 195 MW x 4-hr storage) is expected to reach commercial operation in 2028.
edf-re.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- edf-re.com/project/bonanza-solarstorage/
- eplanning.blm.gov/Project-Home/?id=d4eb41d1-a7f2-f011-8407-001dd803d067
- pv-magazine-usa.com/2023/06/05/blm-to-hold-public-meetings-for-300-mw-bonanza-solar-facility/
- cleanview.co/power-projects/planned/solar-farms/nevada/66908_BZPV/bonanza-solar-and-storage-project
Commercial operation date: EDF power solutions' project page says Bonanza Solar+Storage "is expected to reach commercial operation in 2028," which matches the LBNL date of 2028-09-30. Cleanview lists 2027, but it is an aggregator and the only source with that date.
Developer: The LBNL developer field is null, so there is nothing to compare. The EDF project page, the pv magazine article on the BLM meetings and the Renewables Now PPA story all name EDF as developer of Bonanza in Clark County. The news-extracted 'Arevia Power' applicant comes from a TaiyangNews article on the 700 MW solar / 700 MW BESS project that BLM cleared in September 2024. Utility Dive links that project to Arevia, and it appears to be a different project, so I discarded it.
Status: LBNL shows an active queue entry with an executed IA, and the BLM NEPA register shows a Final EIS but no Record of Decision or construction start. The news-extracted lifecycle facts (ia_executed, 700 MW) come from the misattributed Arevia article, so I did not use them.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Bonanza Solar project is a proposed 450 MW hybrid solar and battery energy storage project located in Clark County, Nevada. The project consists of 300 MW of solar generation and 150 MW of battery storage. It is listed in the CAISO interconnection queue as queue ID CAISO-1649, with an initial queue entry date of April 15, 2019, and a proposed commercial operation date of September 30, 2028.
The project's interconnection agreement (IA) has been executed as of November 22, 2021. The point of interconnection is the Innovation Substation at 230 kV. Bonanza Solar has been the subject of recent news coverage, with 15 articles primarily focusing on regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Innovation Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Innovation Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesSolar queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.