MENIFEE POWER BANK
680 MW storage in Riverside, CA · In queue since April 2019 · Proposed COD October 2025
680 MW
Capacity
1
Components
Battery
7y 3m
In Queue
IA Executed
IA Phase
Signed Dec 2021
Queue → IA
2y 8m
IA → COD
3y 10m
Total Duration
2y 8m
Schedule
9 months past proposed COD
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-10-01
The Menifee Power Bank is a proposed 680 MW battery storage project located in Riverside County, California. The project is interconnected to the CAISO grid under queue ID CAISO-1645. Its queue entry date was April 15, 2019, and the proposed commercial operation date is October 1, 2025. The interconnection agreement for the project was executed on December 14, 2021.
The development project is linked to the existing Menifee Power Bank operating plant (EIA plant ID 66494). The point of interconnection is the Valley Substation 500kV. The project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Valley Substation 500kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ROMOLA_7_004
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26