OBERON
1,036.8 MW hybrid in Riverside, CA · In queue since April 2019 · Proposed COD April 2026
1,036.8 MW
Capacity
2
Components
Solar + Battery
7y 7m
In Queue
IA Executed
IA Phase
Signed Jun 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 2m
IA → COD
3y 10m
Total Duration
3y 2m
Schedule
7 months past proposed COD
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C12
Project under construction
Typical: 18–30 months
Proposed COD: 2026-04-15
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
BLM granted federal approval for the Oberon solar project near Desert Center.
desertsun.comCommercial operation achieved (an actual COD, not a target); BLM and PV Tech report the project operating.
power-technology.comAlphabet announced a definitive agreement to acquire Intersect for US$4.75B; the IPX Power spinoff followed. Oberon's post-deal ownership is not confirmed.
energy-storage.newsResearch sources and reasoning (8 recorded sources)
high confidence at research time
- power-technology.com/projects/oberon-solar-and-storage-project-usa/
- blm.gov/press-release/blm-announces-oberon-solar-project-riverside-county-fully-operational
- renewableenergyworld.com/energy-storage/intersect-power-turns-on-massive-solar-storage-project-in-california/
- pv-tech.org/intersect-power-commissions-679mw-solar-project-in-california-with-250mw-1gwh-of-co-located-storage/
- solvenergy.com/projects/oberon-1
- desertsun.com/story/news/environment/2022/01/13/oberon-sola-blm-land-near-interstate-10-wins-federal-approval/6519795001/
- energy-storage.news/google-acquires-data-centre-and-energy-developer-intersect-for-us4-75-billion/
- solarbuildermag.com/news/ipx-power-relaunches-as-independent-power-producer/
Commercial operation date: Power Technology reports the 'COD achieved' milestone in 2023-11. BLM, Renewable Energy World and PV Tech all report that Oberon is fully operational or commissioned. LBNL's proposed COD of 2026-04-15 is about 2.4 years later, so it is stale.
Developer: The LBNL developer field is null. News, the SOLV Energy project page (owner: Intersect Power) and the PV Tech and Renewable Energy World coverage all name Intersect Power as developer and owner. The BLM applicant, Oberon Solar LLC, is the project shell entity; it comes from news, not from the LBNL filing. Google's acquisition of Intersect and the IPX Power spinoff are corporate-level events, and the sources do not confirm which entity now holds Oberon.
Status: BLM announced the project 'fully operational', and PV Tech reports Intersect started commercial operations. Both contradict LBNL's non-operational flag.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed OBERON project is a 1036.8 MW hybrid solar and battery energy storage development in Riverside County, California. The project consists of 518.4 MW of solar generation and 518.4 MW of battery storage. It is located within the CAISO region and interconnects to Southern California Edison (SCE) at the Red Bluff Substation 500kV.
OBERON entered the CAISO interconnection queue as queue ID CAISO-1642 on April 15, 2019, with a proposed commercial operation date of April 15, 2026. An Interconnection Agreement (IA) was executed on April 27, 2021, and the project currently has an active interconnection status. The project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Red Bluff Substation 500kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OBERON_7_N122
- POI Substation
- Red Bluff Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 6 articlesSolar queue pipeline by status
Data tables and metrics from the InfraSure database.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.