CALYPSO SOLAR
800 MW hybrid in Riverside, CA · In queue since April 2019 · Proposed COD October 2031
800 MW
Capacity
2
Components
Solar + Battery
7y 3m
In Queue
IA Executed
IA Phase
Signed Apr 2023
Queue → IA
4 years
IA → COD
8y 6m
Total Duration
4 years
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2031-10-28
Large Generator Interconnection Agreement executed with CAISO
sourceThe Calypso Solar project is a proposed 800 MW hybrid solar and battery energy storage development in Riverside County, California. The project consists of 400 MW of solar photovoltaic generation paired with 400 MW of battery storage. It is located within the California Independent System Operator (CAISO) region and interconnects to Southern California Edison (SCE) at the Colorado River Substation 230kV.
The project, identified as CAISO-1636 in the interconnection queue, entered the queue on April 15, 2019, and has a proposed commercial operation date of October 28, 2031. The interconnection agreement (IA) for the project has been executed. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Colorado River Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CRIMSN_7_CN3
- POI Substation
- Colorado River Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.