GOLDBACK SOLAR CENTER
500 MW storage in Ventura, CA · In queue since April 2019 · Proposed COD March 2026
500 MW
Capacity
1
Components
Battery
7y 3m
In Queue
IA Executed
IA Phase
Signed Jun 2021
Queue → IA
2y 2m
IA → COD
4y 9m
Total Duration
2y 2m
Schedule
3 months past proposed COD
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-03-31
The Goldback Solar Center is a proposed 500 MW battery storage project in Ventura County, California. The project, located within the CAISO region and under the utility Southern California Edison (SCE), consists entirely of battery storage. It is listed in the CAISO interconnection queue as queue ID CAISO-1619, with an interconnection queue entry date of April 15, 2019, and a proposed commercial operation date of March 31, 2026.
The project's Interconnection Agreement (IA) has been executed as of June 21, 2021. The point of interconnection (POI) is the Moorpark Substation 230 kV. The Goldback Solar Center development has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Ventura
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Moorpark Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MOORPARK_6_N005
- POI Substation
- Moorpark Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about GOLDBACK SOLAR CENTERForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.