GOLDBACK SOLAR CENTER
500 MW storage in Ventura, CA · In queue since April 2019 · Proposed COD April 2029
500 MW
Capacity
1
Components
Battery
7y 7m
In Queue
IA Executed
IA Phase
Signed Jun 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
7y 10m
Total Duration
2y 2m
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C12
Project under construction
Typical: 6–18 months
Proposed COD: 2029-04-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-1619
- cleanview.co/power-projects/planned/battery-storage-projects/california/1619_storage/goldback-solar-center
- app.nrgmap.com/queues/caiso-1619
- futuregrid.io/genprojects/goldback-solar-center/
Commercial operation date: Only the LBNL proposed COD (2029-04-01) is available. Cleanview and interconnection.fyi repeat 2029, but they appear to derive it from the queue data, so they are not independent confirmation. FutureGrid's '2026' is an uncorroborated outlier and I discounted it.
Developer: The LBNL developer field is null and no search result names a developer or parent company. The Avantus article is about the Aratina project in Kern County and does not mention Goldback.
Status: LBNL lists the project as active with an executed IA, and the aggregators (interconnection.fyi, NRG Map, InterXData) agree. No source shows it withdrawn, suspended or under construction.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Goldback Solar Center is a proposed 500 MW battery storage project in Ventura County, California. The project, located within the CAISO region and under the utility Southern California Edison (SCE), consists entirely of battery storage. It is listed in the CAISO interconnection queue as queue ID CAISO-1619, with an interconnection queue entry date of April 15, 2019, and a proposed commercial operation date of March 31, 2026.
The project's Interconnection Agreement (IA) has been executed as of June 21, 2021. The point of interconnection (POI) is the Moorpark Substation 230 kV. The Goldback Solar Center development has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Ventura
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Moorpark Substation 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MOORPARK_6_N005
- POI Substation
- Moorpark Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
GOLDBACK SOLAR CENTER
Data-driven briefing on GOLDBACK SOLAR CENTER — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.