COMMERCE ENERGY STORAGE
250 MW storage in Los Angeles, CA · In queue since April 2019 · Proposed COD June 2026
250 MW
Capacity
1
Components
Battery
7y 3m
In Queue
IA Executed
IA Phase
Signed Jan 2022
Queue → IA
2y 9m
IA → COD
4y 5m
Total Duration
2y 9m
Schedule
1 months past proposed COD
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-06-01
CEQA Mitigated Negative Declaration filed for 250MW battery storage construction and operation
sourceThe Commerce Energy Storage project is a proposed 250 MW battery storage development in Los Angeles County, California. The project is located in the CAISO region and interconnects to Southern California Edison (SCE) at the Laguna Bell Substation 230kV. It entered the CAISO interconnection queue as queue ID CAISO-1611 on April 15, 2019, with a proposed commercial operation date of June 1, 2026. An Interconnection Agreement (IA) was executed on January 12, 2022.
The project consists of 250 MW of battery storage capacity. The Commerce Energy Storage project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Laguna Bell Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LAGUBELL_6_N005
- POI Substation
- Laguna Bell Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about COMMERCE ENERGY STORAGEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.