COMMERCE ENERGY STORAGE
250 MW storage in Los Angeles, CA · In queue since April 2019 · Proposed COD June 2028
250 MW
Capacity
1
Components
Battery
7y 7m
In Queue
IA Executed
IA Phase
Signed Jan 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 9m
IA → COD
6y 5m
Total Duration
2y 9m
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C12
Project under construction
Typical: 6–18 months
Proposed COD: 2028-06-01
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 24, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
CEQA Mitigated Negative Declaration filed for 250MW battery storage construction and operation
ceqanet.lci.ca.govProposed commercial operation date per CAISO queue
caiso.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- ceqanet.lci.ca.gov/2022040355
- wecc.org/sites/default/files/documents/progress_report/2024/Commerce%20ES%202024%20APR.pdf
- wecc.org/sites/default/files/documents/progress_report/2026/Comerce%20ES%202026%20APR.pdf
- caiso.com/documents/list-of-large-generator-interconnection-agreements-and-small-generator-interconnection-agreements.pdf
- caiso.com/documents/publicqueuereport.xlsx
Commercial operation date: LBNL queue shows proposed COD of June 2026. No press releases or news articles found with updated COD targets. WECC progress reports from 2024 and 2026 confirm project remains active but don't specify revised COD.
Developer: LBNL filing entity is 'Commerce Energy Storage, LLC' (confirmed in WECC reports and CAISO interconnection agreements). No press releases or corporate announcements found identifying a parent operating company. The LLC appears to be the project entity without public disclosure of ultimate ownership.
Status: LBNL shows 'active' status with IA executed in January 2022. CEQA filings from April 2022 show environmental clearance obtained. Ground lease signing and WECC progress reports through 2026 confirm project remains in development.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Commerce Energy Storage project is a proposed 250 MW battery storage development in Los Angeles County, California. The project is located in the CAISO region and interconnects to Southern California Edison (SCE) at the Laguna Bell Substation 230kV. It entered the CAISO interconnection queue as queue ID CAISO-1611 on April 15, 2019, with a proposed commercial operation date of June 1, 2026. An Interconnection Agreement (IA) was executed on January 12, 2022.
The project consists of 250 MW of battery storage capacity. The Commerce Energy Storage project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Laguna Bell Substation 230kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LAGUBELL_6_N005
- POI Substation
- Laguna Bell Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.