TANAGER STORAGE
200 MW storage in Santa Clara, CA · In queue since April 2019 · Proposed COD December 2027
200 MW
Capacity
1
Components
Battery
7y 3m
In Queue
IA Executed
IA Phase
Signed Sep 2023
Queue → IA
4y 5m
IA → COD
4y 3m
Total Duration
4y 5m
Study Phase
C12
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-15
The Tanager Storage project is a proposed 200 MW battery energy storage system located in Santa Clara County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-1550. Its queue entry date was April 15, 2019, and the proposed commercial operation date is December 15, 2027.
The project's Interconnection Agreement (IA) was executed on December 22, 2021. The designated utility is Pacific Gas and Electric (PGAE), and the point of interconnection (POI) is the Los Esteros 230 kV substation. The project is currently listed as active in the CAISO queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Santa Clara
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Los Esteros 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LECEFGT2_7_B1
- POI Substation
- Los Esteros Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about TANAGER STORAGEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.