IRVING STORAGE
782.79 MW storage in Monterey, CA · In queue since May 2019 · Proposed COD August 2030
782.79 MW
Capacity
1
Components
Battery
7y 6m
In Queue
IA Executed
IA Phase
Signed Jul 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
9y 1m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; ISP
Project under construction
Typical: 6–18 months
Proposed COD: 2030-08-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-1539
- docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M534/K048/534048570.PDF
- cleanview.co/power-projects/planned/battery-storage-projects/arkansas/1539_storage/irving-storage
Commercial operation date: Only the LBNL proposed COD of 2030-08-01 is usable. Cleanview's 'Expected online 2025' is a single aggregator claim with no developer or press backing, and it looks like stale queue data. The news-extracted 2027 COD belongs to a Georgia Power project in Jefferson County, not this one.
Developer: LBNL lists no developer. The news-extracted 'Georgia Power' and 'Moss Landing Phase II (Vistra)' facts come from unrelated projects (a Georgia groundbreaking and an operational Moss Landing expansion). They do not mention Irving Storage and were rejected. No search result names a developer.
Status: LBNL shows 'active' with IA Executed, and interconnection.fyi independently lists CAISO-1539 as Active. No source indicates withdrawal or construction.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Irving Storage project is a proposed 782.79 MW battery storage project located in Monterey County, California. Interconnecting to PG&E via the Moss Landing 500 kV point of interconnection, the project is in the CAISO interconnection queue as queue ID CAISO-1539, with an initial queue entry date of May 7, 2019. The developer anticipates a commercial operation date of November 30, 2025.
The project's interconnection agreement was executed on July 12, 2021. The Irving Storage project has been the subject of recent news coverage, with at least 10 articles appearing in the press.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Moss Landing 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesGeothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.