IRVING STORAGE
782.79 MW storage in Monterey, CA · In queue since May 2019 · Proposed COD November 2025
782.79 MW
Capacity
1
Components
Battery
7y 2m
In Queue
IA Executed
IA Phase
Signed Jul 2021
Queue → IA
2y 2m
IA → COD
4y 4m
Total Duration
2y 2m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-11-30
The Irving Storage project is a proposed 782.79 MW battery storage project located in Monterey County, California. Interconnecting to PG&E via the Moss Landing 500 kV point of interconnection, the project is in the CAISO interconnection queue as queue ID CAISO-1539, with an initial queue entry date of May 7, 2019. The developer anticipates a commercial operation date of November 30, 2025.
The project's interconnection agreement was executed on July 12, 2021. The Irving Storage project has been the subject of recent news coverage, with at least 10 articles appearing in the press.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Moss Landing 500 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26