KETTLE SOLAR ONE
180 MW hybrid in San Diego, CA · In queue since April 2018 · Proposed COD January 2027
180 MW
Capacity
2
Components
Solar + Battery
8y 3m
In Queue
IA Executed
IA Phase
Signed May 2020
Queue → IA
2y 1m
IA → COD
6y 8m
Total Duration
2y 1m
Study Phase
C11
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-01-13
KETTLE SOLAR ONE is a proposed 180 MW hybrid solar and battery project located in San Diego County, California. The development project consists of 90 MW of solar generation paired with 90 MW of battery storage. Interconnection is planned via the Carrizo Gorge Switchyard 138 kV.
The project is listed in the CAISO interconnection queue as entry CAISO-1532, with an original queue entry date of April 16, 2018. The proposed commercial operation date is October 31, 2026. An Interconnection Agreement (IA) has been executed as of May 14, 2020. KETTLE SOLAR ONE has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Diego
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Carrizo Gorge Switchyard 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about KETTLE SOLAR ONEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.