LAS CAMAS 3
202.5 MW hybrid in Merced, CA · In queue since April 2018 · Proposed COD December 2027
202.5 MW
Capacity
2
Components
Solar + Battery
8y 7m
In Queue
IA Executed
IA Phase
Signed Mar 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 11m
IA → COD
5y 9m
Total Duration
3y 11m
Study Phase
C11
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C11
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed for Las Camas 3 (CAISO Q1456), connecting at Los Banos 230 kV
powerplantsinfo.orgProposed commercial operation date of December 31, 2027 per CAISO queue filing (202.5 MW total: ~100 MW solar + ~102.5 MW battery)
powerplantsinfo.orgResearch sources and reasoning (10 recorded sources)
low confidence at research time
- caiso.com/documents/briefing-resourcesavailable-nearterminterconnection.pdf
- interconnection.fyi/projects/state/CA/merced-county
- docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M534/K048/534048570.PDF
- infrasure.ai/project/caiso-1456-las-camas-3
- interconnection.fyi/projects/market/CAISO
- cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/summer-2021-reliability/tracking-energy-development/cpuc_2025_letter_to_pge-(1).pdf
- pge.com/assets/pge/docs/regulation/federal-energy-regulatory-commission/ferc-form-1-2025.pdf
- interconnection.fyi/project/caiso-1456
- interxdata.com/projects/las-camas-3-caiso-public-queue-1456/
- powerplantsinfo.org/project/caiso-1456-las-camas-3
Commercial operation date: The proposed COD of 2027-12-31 comes solely from the LBNL queue snapshot; powerplantsinfo.org and interxdata.com echo the same date but are derived from the same CAISO queue data, not independent developer announcements. No press releases or financing-backed target dates have been located.
Developer: LBNL lists the developer as null and no search results identify the developer or project sponsor by name; the PG&E FERC Form 1 prefix 'MMA' in 'MMA-Q1456-Las Camas 3-ISO53203' may reference a counterparty code but cannot be resolved to a company name from available sources.
Status: LBNL confirms IA Executed status with a signed date of 2022-03-28; interxdata.com (August 2026) and interconnection.fyi both confirm 'active' queue status with no indication of withdrawal or suspension.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Las Camas 3 project is a proposed 202.5 MW hybrid solar and battery energy storage project located in Merced County, California. The project consists of a 102.5 MW solar array coupled with a 100 MW battery energy storage system. It is interconnected within the California Independent System Operator (CAISO) queue as queue ID CAISO-1456. The project entered the queue on April 16, 2018, and has a proposed commercial operation date of December 31, 2027.
The interconnection agreement (IA) for Las Camas 3 has been executed as of March 28, 2022. The point of interconnection (POI) is the Los Banos 230 kV substation. The project is currently listed as active in the CAISO interconnection queue. Recent news coverage has discussed the project's progress.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Merced
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Los Banos 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SNTANLA_6_N001
- POI Substation
- Los Banos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
LAS CAMAS 3 in Alaska queue pipeline — 1 projects by technology and status
Data-driven briefing on LAS CAMAS 3 — fleet, generation, financial, and news signals.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
LAS CAMAS 3
Data-driven briefing on LAS CAMAS 3 — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.