SALOON ENERGY STORAGE
150 MW storage in Colusa, CA · In queue since April 2018 · Proposed COD July 2027
150 MW
Capacity
1
Components
Battery
8y 7m
In Queue
IA Executed
IA Phase
Signed Feb 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5y 10m
IA → COD
3y 5m
Total Duration
5y 10m
Study Phase
C11
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C11
Project under construction
Typical: 6–18 months
Proposed COD: 2027-07-13
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with CAISO for 150 MW BESS in Colusa County
interconnection.fyiSaloon Energy Storage LLC filed Major Use Permit application (PD-25-6) with Colusa County; CEQA review initiated
ceqanet.lci.ca.govProposed commercial operation date per CAISO queue (CAISO-1444)
interconnection.fyiResearch sources and reasoning (4 recorded sources)
low confidence at research time
- ceqanet.lci.ca.gov/2025070064
- ceqanet.lci.ca.gov/2025070064/2
- cleanview.co/power-projects/planned/battery-storage-projects/california/1444_storage/saloon-energy-storage
- interconnection.fyi/project/caiso-1444
Commercial operation date: LBNL queue lists proposed COD of 2027-07-13; interconnection.fyi independently confirms the same date. No source provides a conflicting target, though the active CEQA permitting process as of late 2025 makes this timeline ambitious.
Developer: LBNL lists no developer; Colusa County CEQAnet filings (July–December 2025) identify 'Saloon Energy Storage LLC' as the project applicant, but no parent or operating company is publicly identified. News-extracted facts referencing Enlight Renewable Energy pertain to an unrelated Arizona solar+BESS project (Salt River Project offtake, $1.44B financing) and are excluded as misattributed.
Status: LBNL confirms IA Executed on 2024-02-27 and active queue standing. CEQAnet records from July and December 2025 confirm county land-use permitting is underway, consistent with pre-construction development.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Saloon Energy Storage project is a proposed 150 MW battery storage project located in Colusa County, California. Interconnection is managed through CAISO, with queue ID CAISO-1444. The project entered the queue on April 16, 2018, and has a proposed commercial operation date of July 13, 2027. The point of interconnection is the Cortina 115 kV substation.
The project's Interconnection Agreement (IA) was executed on February 27, 2024. Saloon Energy Storage has been the subject of recent news coverage, with 11 articles categorized as industry, deals, regulatory, development, and hazards.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Colusa
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Cortina 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CORTINA_1_N106
- POI Substation
- Cortina Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesSALOON ENERGY STORAGE Battery Storage in ISO New England growth signals — PPAs, construction, new projects
Data-driven briefing on SALOON ENERGY STORAGE — fleet, generation, financial, and news signals.
SALOON ENERGY STORAGE Battery Storage growth signals — PPAs, construction, new projects
Data-driven briefing on SALOON ENERGY STORAGE — fleet, generation, financial, and news signals.
SALOON ENERGY STORAGE
Data-driven briefing on SALOON ENERGY STORAGE — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.