HEARTLAND 2
228.343 MW hybrid in Fresno, CA · In queue since May 2017 · Proposed COD June 2028
228.343 MW
Capacity
2
Components
Solar + Battery
9y 6m
In Queue
IA Executed
IA Phase
Signed Dec 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
6y 7m
IA → COD
4y 6m
Total Duration
6y 7m
Study Phase
C10
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C10
Project under construction
Typical: 18–30 months
Proposed COD: 2028-06-30
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed for HEARTLAND 2 (CAISO queue 1380) on December 4, 2023
docs.cpuc.ca.govProposed commercial operation date per CAISO interconnection queue filing
interconnection.fyiResearch sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/caiso-1380
- fresnocountyca.gov/files/sharedassets/county/v/1/vision-files/files/55418-scarlet-solar-draft-eir.pdf
- docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M534/K048/534048570.PDF
- caiso.com/documents/briefing-resourcesavailable-nearterminterconnection.pdf
- solarbuildermag.com/projects/california-approves-worlds-largest-solar-storage-plant-projects-weekly/
Commercial operation date: Only the LBNL queue snapshot provides a proposed COD of 2028-06-30; no news or research sources confirm or contradict this date, leaving it as the sole data point.
Developer: LBNL lists no developer; the Fresno County Scarlet Solar draft EIR identifies 'Heartland 2, LLC' as an entity located west of Derrick Ave near the project area. No parent operating company has been publicly identified in any source.
Status: LBNL confirms IA Executed status dated 2023-12-04; the CAISO queue summary (interconnection.fyi) and the December 2023 CAISO near-term interconnection briefing both confirm the project remains active at 150 MW photovoltaic plus battery storage in Fresno County.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The HEARTLAND 2 project is a proposed 156.05 MW solar generation project located in Fresno County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-1380, with an original queue entry date of May 1, 2017. The proposed commercial operation date is June 30, 2028. The interconnection agreement (IA) for the project was executed on December 4, 2023. The point of interconnection is Tranquility 230 kV.
The HEARTLAND 2 development project has been the subject of recent news coverage, with eight articles categorized as regulatory, deals, and industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
ERIS
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlescan you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
HEARTLAND 2
Data-driven briefing on HEARTLAND 2 — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.