CORBY (CAISO-1270) — Project Summary

Queue ID
CAISO-1270
Capacity
313.5 MW
Technology
Battery
Status
active
Location
Solano, CA
Region
CAISO
Developer
—
IA Status
IA Executed

CORBY

CAISO-1270BetaActiveBatteryCAISOLBNL + Live

313.5 MW storage in Solano, CA · In queue since May 2016 · Proposed COD June 2027

BA: CISOISO/RTO: CAISONERC: WECCRC: RCW

313.5 MW

Capacity

1

Components

Battery

10y 6m

In Queue

IA Executed

IA Phase

Signed Jun 2021

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

5y 1m

IA → COD

6 years

Total Duration

5y 1m

Study Phase

C09

Construction75%
Queue EntryMay 2, 2016

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementJun 9, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Active sheet; IA Executed; C09

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-06-01

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activityproduct_announcementCBS News · 2025-07-24

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jun 1, 2027
From queue filing
Developer in saved assessment
NextEra Energy Resources
Filed as Corby Energy Storage, LLC
Status at research time
Active
Active, IA executed (2021-06-09). Still in CEC licensing review, with EIR extension filed in March 2026 and final public hearings in Aug-Sept 2026. No permit approval or construction start reported.
Financing
Not recorded
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. pressdemocrat.com/2026/03/04/corby-bess-project-files-for-eir-extension/
  2. cbsnews.com/sacramento/news/vacaville-neighbors-push-back-proposed-battery-plant/
  3. energy.ca.gov/powerplant/battery-storage-system/corby-battery-energy-storage-system-project
  4. nexteraenergyresources.com/corby-project.html
  5. rtoinsider.com/142040-cec-ponders-fate-corby-battery-energy-storage-system/
  6. thereporter.com/2026/10/14/corby-bess-project-faces-more-environmental-scrutiny/

Commercial operation date: Only the LBNL proposed COD (2027-06-01) is available. None of the news or search snippets gives a developer COD target. The project is still in CEC permitting (EIR and public hearings through Sept-Oct 2026), so the LBNL date looks optimistic but cannot be corrected from the evidence.

Developer: LBNL has no developer listed. The CEC docket names Corby Energy Storage, LLC as applicant, and the NextEra Energy Resources project page and CBS/Press Democrat coverage identify NextEra as the sponsor. The legal entity comes from the CEC filing, not from LBNL.

Status: LBNL shows an active queue entry with an executed IA. News and CEC sources show the project is still pre-permit and not operational.

Project lifecycle
as of 2026-03-09
OperationalNoThe Press Democrat · 2026-03-09
TechnologyBatteryThe Press Democrat · 2026-03-09
DeveloperNextEra EnergyThe Press Democrat · 2026-03-09
PPA offtakerClean Power SFThe Press Democrat · 2026-03-09
Permit decisionpendingThe Press Democrat · 2026-03-09

About

Saved background

Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The CORBY project is a proposed 313.5 MW battery storage project located in Solano County, California. Interconnecting to the PG&E utility, the project is in the CAISO interconnection queue as entry CAISO-1270, with a queue entry date of May 2, 2016. The proposed commercial operation date is June 1, 2027. The project's Interconnection Agreement (IA) was executed on June 9, 2021.

The development project has been the subject of recent news coverage, with seven articles categorized as regulatory, industry, and grid-related.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • CAISO queue source as of: Oct 24, 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

CA

County

Solano

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

—

Utility

PGAE

Entity

CAISO

Service Type

NRIS

Point of Interconnection

Vaca-Dixon 230 kV

Data Source

LBNL + Live

ApplicantCorby Energy Storage LLC±The Press Democrat · 2026-03-09
CompanyNextEra EnergyCBS News · 2025-07-24
AgencyCalifornia Energy Commission±The Press Democrat · 2026-03-09
RulingNotice±The Press Democrat · 2026-03-09
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.