CORBY
313.5 MW storage in Solano, CA · In queue since May 2016 · Proposed COD June 2027
313.5 MW
Capacity
1
Components
Battery
10y 6m
In Queue
IA Executed
IA Phase
Signed Jun 2021
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
5y 1m
IA → COD
6 years
Total Duration
5y 1m
Study Phase
C09
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C09
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
medium confidence at research time
- pressdemocrat.com/2026/03/04/corby-bess-project-files-for-eir-extension/
- cbsnews.com/sacramento/news/vacaville-neighbors-push-back-proposed-battery-plant/
- energy.ca.gov/powerplant/battery-storage-system/corby-battery-energy-storage-system-project
- nexteraenergyresources.com/corby-project.html
- rtoinsider.com/142040-cec-ponders-fate-corby-battery-energy-storage-system/
- thereporter.com/2026/10/14/corby-bess-project-faces-more-environmental-scrutiny/
Commercial operation date: Only the LBNL proposed COD (2027-06-01) is available. None of the news or search snippets gives a developer COD target. The project is still in CEC permitting (EIR and public hearings through Sept-Oct 2026), so the LBNL date looks optimistic but cannot be corrected from the evidence.
Developer: LBNL has no developer listed. The CEC docket names Corby Energy Storage, LLC as applicant, and the NextEra Energy Resources project page and CBS/Press Democrat coverage identify NextEra as the sponsor. The legal entity comes from the CEC filing, not from LBNL.
Status: LBNL shows an active queue entry with an executed IA. News and CEC sources show the project is still pre-permit and not operational.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The CORBY project is a proposed 313.5 MW battery storage project located in Solano County, California. Interconnecting to the PG&E utility, the project is in the CAISO interconnection queue as entry CAISO-1270, with a queue entry date of May 2, 2016. The proposed commercial operation date is June 1, 2027. The project's Interconnection Agreement (IA) was executed on June 9, 2021.
The development project has been the subject of recent news coverage, with seven articles categorized as regulatory, industry, and grid-related.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Solano
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Vaca-Dixon 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 5 articlesBattery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.