POMEGRANATE
479 MW hybrid in Kings, CA · In queue since May 2016 · Proposed COD December 2027
479 MW
Capacity
2
Components
Solar + Battery
10y 6m
In Queue
IA Executed
IA Phase
Signed Jan 2020
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 8m
IA → COD
7y 11m
Total Duration
3y 8m
Study Phase
C09
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C09
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (2 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/california/1243_storage/pomegranate
- interconnection.fyi/projects/market/CAISO
Commercial operation date: The LBNL proposed COD is 2027-12-31. Cleanview says the project is 'Expected online 2027', which matches, but it is probably derived from the same queue data. No press release or news article gives an independent, financing-backed date.
Developer: The LBNL developer field is null and no search result names a developer or operating company. The Hanford Sentinel Westlands Solar Park article is about 66 months old and does not clearly link the project to Pomegranate, so I did not use it.
Status: LBNL lists the status as active with an executed IA, and interconnection.fyi also shows it as Active. Nothing in the search results contradicts this or shows a withdrawal.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The POMEGRANATE project is a proposed 479 MW hybrid solar and battery energy storage project located in Kings County, California. The development project consists of a 254 MW solar photovoltaic component and a 225 MW battery energy storage system. It is interconnected to the CAISO grid at the Gates 230 kV point of interconnection, and is in the CAISO interconnection queue as entry CAISO-1243, with a queue entry date of May 2, 2016.
The project's proposed commercial operation date is December 31, 2027. An Interconnection Agreement (IA) for the project has been executed as of January 7, 2020. The interconnecting utility is PG&E.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Kings
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Gates 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FIFTHS_7_N003
- POI Substation
- Gates Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
AEP Jacksonville Solar Project
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.