FALLBROOK ENERGY STORAGE
69.6 MW storage in San Diego, CA · In queue since April 2015 · Proposed COD March 2026
69.6 MW
Capacity
1
Components
Battery
11y 3m
In Queue
IA Executed
IA Phase
Signed Mar 2023
Queue → IA
7y 11m
IA → COD
3 years
Total Duration
7y 11m
Schedule
4 months past proposed COD
Study Phase
C08
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-03-06
The Fallbrook Energy Storage project is a proposed 69.6 MW battery storage project located in San Diego County, California. Interconnecting to the CAISO grid via the Avocado Substation 69 kV point of interconnection, the project entered the CAISO queue as queue ID CAISO-1169 on April 30, 2015. The proposed commercial operation date is March 6, 2026, and the interconnection agreement has been executed.
The development project is linked to the existing Fallbrook Energy Storage operating plant (EIA ID 61365). Recent news coverage indicates interest in the project, with articles focusing on grid applications and industry developments.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
San Diego
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Avocado Substation 69 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AVOCADO_6_N001
- POI Substation
- Avocado
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about FALLBROOK ENERGY STORAGEForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.