LUNA VALLEY SOLAR
372.5 MW hybrid in Fresno, CA · In queue since April 2015 · Proposed COD December 2028
372.5 MW
Capacity
2
Components
Solar + Battery
11y 3m
In Queue
IA Executed
IA Phase
Signed Nov 2018
Queue → IA
3y 7m
IA → COD
10y 1m
Total Duration
3y 7m
Study Phase
C08
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-29
The LUNA VALLEY SOLAR project is a proposed 372.5 MW hybrid solar and battery energy storage project located in Fresno County, California. The development project consists of a 204 MW solar array coupled with a 168.5 MW battery energy storage system. It is interconnected to the CAISO grid at the Tranquility 230 kV point of interconnection.
The project, developed under the utility PGAE, entered the CAISO interconnection queue as queue ID CAISO-1129 on April 30, 2015, and has a proposed commercial operation date of December 29, 2028. An Interconnection Agreement (IA) was executed on November 25, 2018. The LUNA VALLEY SOLAR project has been the subject of recent news coverage, with six articles appearing in industry, regulatory, and deals publications.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26