LUNA VALLEY SOLAR
372.5 MW hybrid in Fresno, CA · In queue since April 2015 · Proposed COD December 2028
372.5 MW
Capacity
2
Components
Solar + Battery
11y 7m
In Queue
IA Executed
IA Phase
Signed Nov 2018
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 7m
IA → COD
10y 1m
Total Duration
3y 7m
Study Phase
C08
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Active sheet; IA Executed; C08
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-29
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Clearway closed more than $700M of construction financing for Luna Valley Solar (200 MW) and Daggett Storage (113.5 MW).
clearwayenergygroup.comClearway announced the start of construction at Luna Valley alongside the financing close.
clearwayenergygroup.comResearch sources and reasoning (6 recorded sources)
medium confidence at research time
- clearwayenergygroup.com/press-releases/clearway-closes-financing-and-starts-construction-on-solar-and-battery-energy-storage-facilities-in-california/
- pv-magazine-usa.com/2024/07/25/california-replacing-nuclear-with-solar-plus-storage/
- gvwire.com/2024/07/23/new-solar-farm-in-western-fresno-county-will-power-80000-homes/
- mercomcapital.com/clearway-secures-700-million-financing-for-solar-and-storage-project/
- sec.gov/Archives/edgar/data/1567683/000110465924077514/tm2418726d1_8k.htm
- gem.wiki/Luna_Valley_solar_farm
Commercial operation date: GV Wire (2024-07-23), reporting on the financing close and construction start, gives an expected COD of 2025, versus LBNL's 2028-12-29, a gap of about 3-4 years. Only one source states a COD. The Clearway press release confirms construction began in July 2024, which supports the earlier date. Global Energy Monitor lists the farm as operating, but gives no date.
Developer: The LBNL developer field is blank. Clearway's press release, its SEC 8-K, pv magazine USA and Mercom all name Clearway as developer and owner, and none conflict. The CEQA record names a project entity, Luna Valley Solar 1, LLC, but it is not the LBNL filing entity.
Status: The Clearway press release (2024-07-22) and the 8-K say construction began after financing closed. The LBNL 'active' status is still true for queue position, but it understates the ground reality. No source dated after construction start confirms commercial operation.
About
Generated Apr 10, 2026 · Predates Oct 24, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The LUNA VALLEY SOLAR project is a proposed 372.5 MW hybrid solar and battery energy storage project located in Fresno County, California. The development project consists of a 204 MW solar array coupled with a 168.5 MW battery energy storage system. It is interconnected to the CAISO grid at the Tranquility 230 kV point of interconnection.
The project, developed under the utility PGAE, entered the CAISO interconnection queue as queue ID CAISO-1129 on April 30, 2015, and has a proposed commercial operation date of December 29, 2028. An Interconnection Agreement (IA) was executed on November 25, 2018. The LUNA VALLEY SOLAR project has been the subject of recent news coverage, with six articles appearing in industry, regulatory, and deals publications.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- CAISO queue source as of: Oct 24, 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
NRIS
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- Q1032C2_7_N001
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlescan you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
Luna Valley
Data-driven briefing on Luna Valley — fleet, generation, financial, and news signals.
can you provide me with the capacity factor for allrenewable facilities in 2024
Data tables and metrics from the InfraSure database.
LUNA VALLEY SOLAR
Data-driven briefing on LUNA VALLEY SOLAR — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.