BPA-G1069
20 MW generation in Harney, OR · In queue since July 2024 · Proposed COD March 2025
20 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Phase
COD target: 2025
Total Duration
8 months
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-31
BPA-G1069 is a proposed 20 MW solar generation project located in Harney County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of July 23, 2024. The proposed commercial operation date is March 31, 2025.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is at the Harney 115kV Substation, with coordinates 43.439458, -118.704502 for 9.9 MW and 43.438922, -118.704502 for 9.9 MW.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Harney
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
ERIS
Point of Interconnection
43.439458, -118.704502 for 9.9 MW; 43.438922, -118.704502 for 9.9 MW at Harney 115kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project BPA-G1069Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.