BPA-G1018
1,023.6 MW hybrid in Klamath, OR · In queue since November 2023 · Proposed COD November 2030
1,023.6 MW
Capacity
2
Components
Solar + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-11-15
BPA-G1018 is a proposed solar and battery hybrid project located in Klamath County, Oregon, with a total capacity of 1023.6 MW. The project consists of a 508.5 MW solar component and a 515.1 MW battery energy storage system. It is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of November 21, 2023, and a proposed commercial operation date of November 15, 2030.
The interconnection agreement (IA) status for BPA-G1018 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the LaPine-Chiloquin No. 1 230kV line.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
LaPine-Chiloquin No. 1 230kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.