BPA-G0841
600 MW hybrid in Lake, OR · In queue since February 2023 · Proposed COD December 2028
600 MW
Capacity
2
Components
Solar + Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
BPA-G0841 is a proposed 600 MW hybrid Solar+Battery project located in Lake County, Oregon. The project consists of a 400 MW solar component and a 200 MW battery energy storage system. It is listed in the Bonneville Power Administration (BPA) interconnection queue with a queue entry date of February 15, 2023, and a proposed commercial operation date of December 1, 2028.
The interconnection request, under queue ID BPA-G0841, has an interconnection agreement (IA) status of "In Progress (unknown study)". The proposed point of interconnection (POI) is on the Grizzly-Summer Lake #1 or Grizzly-Captain Jack #1 500 kV lines.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Grizzly-Summer Lake #1 or Grizzly-Captain Jack #1 500 kV lines.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.