BPA-G0841
600 MW hybrid in Lake, OR · In queue since February 2023 · Proposed COD December 2028
600 MW
Capacity
2
Components
Solar + Battery
3y 5m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
5y 10m
Study Phase
Transition Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
BPA-G0841 is a proposed 600 MW hybrid Solar+Battery project located in Lake County, Oregon. The project consists of a 400 MW solar component and a 200 MW battery energy storage system. It is listed in the Bonneville Power Administration (BPA) interconnection queue with a queue entry date of February 15, 2023, and a proposed commercial operation date of December 1, 2028.
The interconnection request, under queue ID BPA-G0841, has an interconnection agreement (IA) status of "In Progress (unknown study)". The proposed point of interconnection (POI) is on the Grizzly-Summer Lake #1 or Grizzly-Captain Jack #1 500 kV lines.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
NRIS/ERIS
Point of Interconnection
Grizzly-Summer Lake #1 or Grizzly-Captain Jack #1 500 kV lines.
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.