BPA-G0826
560 MW hybrid in Klamath, OR · In queue since November 2022 · Proposed COD December 2027
560 MW
Capacity
2
Components
Solar + Battery
3y 8m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
Total Duration
5y 1m
Study Phase
Transition Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
BPA-G0826 is a proposed 560 MW hybrid solar and battery project located in Klamath County, Oregon. The development project consists of 280 MW of solar capacity and 280 MW of battery storage. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of November 20, 2022, and a proposed commercial operation date of December 31, 2027.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is primarily the Grizzly - Summer Lake No 1 500 kV line, with a secondary POI at the Grizzly - Captain Jack No 1 500 kV line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
NRIS/ERIS
Point of Interconnection
Primary: Grizzly - Summer Lake No 1 500 kV line. Secondary: Grizzly - Captain Jack No 1 500 kV line.
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.