BPA-G0684
705 MW hybrid in Benton, WA · In queue since July 2021 · Proposed COD October 2024
705 MW
Capacity
2
Components
Solar + Battery
5 years
In Queue
In Progress (unknown study)
IA Phase
COD target: 2024
Total Duration
3y 3m
Schedule
22 months past proposed COD
Study Phase
Transition Late Stage
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
The proposed project BPA-G0684 is a 705 MW hybrid Solar+Battery project located in Benton County, Washington. The project, which consists of 470 MW of solar capacity and 235 MW of battery storage, is interconnected to the Bonneville Power Administration (BPA) via the Wautoma 500 kV Substation.
The project is currently active in the BPA interconnection queue, having entered on July 23, 2021, with a proposed commercial operation date of October 1, 2024. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The project has appeared in recent news.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
ERIS
Point of Interconnection
Wautoma 500 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.