Project BPA-G0594 — Project Summary

Queue ID
BPA-G0594
Capacity
1 MW
Technology
Solar
Status
active
Location
Lane, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G0594

BPA-G0594BetaActiveSolarBPALBNL

1 MW generation in Lane, OR · In queue since July 2018 · Proposed COD September 2018

BA: BPATNERC: WECCRC: RCW

1 MW

Capacity

1

Components

Solar

7y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2018

Interconnection

Total Duration

2 months

Schedule

93 months past proposed COD

In Study38%
Queue EntryJul 18, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2018-09-21

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

BPA-G0594 is a proposed 1 MW solar generation project located in Lane County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of July 18, 2018. The proposed commercial operation date is September 21, 2018.

The interconnection agreement (IA) status for BPA-G0594 is listed as "In Progress (unknown study)". The point of interconnection (POI) is with EWEB's system, with the exact location to be determined.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Lane

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

EWEB's system. Exact location TBD.

Data Source

LBNL

Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No Ask reports yet for this entity.

Ask about Project BPA-G0594
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.