BPA-G0585
313 MW generation in Klickitat, WA · In queue since March 2018 · Proposed COD July 2021
313 MW
Capacity
1
Components
Wind
8y 4m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2021
Total Duration
3y 4m
Schedule
61 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-07-01
BPA-G0585 is a proposed wind generation project with a total capacity of 313 MW. The project is located in Klickitat County, Washington, and is interconnected to the Bonneville Power Administration (BPA) grid. The point of interconnection is the McNary-John Day 500kV Tap, also known as BPA's "G0585 Substation".
The project entered the BPA interconnection queue on March 19, 2018, with a proposed commercial operation date of July 1, 2021. The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Klickitat
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
NRIS/ERIS
Point of Interconnection
McNary-John Day 500kV Tap (BPA's "G0585 Substation")
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project BPA-G0585Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.