BPA-G0558
500 MW generation in Benton, WA · In queue since February 2017 · Proposed COD December 2019
500 MW
Capacity
1
Components
Wind
9y 5m
In Queue
Facility Study
IA Phase
COD target: 2019
Total Duration
2y 10m
Schedule
80 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-12-01
BPA-G0558 is a proposed 500 MW wind generation project located in Benton County, Washington. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of February 21, 2017. The proposed commercial operation date is December 1, 2019.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is at BPA's Ashe - Marion 500 kV line, Mile 26, Tower 4, and BPA's McNary - John Day 500 kV line, Mile 4, Tower 1.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
NRIS/ERIS
Point of Interconnection
BPA's Ashe - Marion 500 kV, Mile 26, Tower 4; BPA's McNary - John Day 500 kV, Mile 4, Tower 1
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project BPA-G0558Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.