BPA-G0539
600 MW generation in Deschutes, OR · In queue since May 2016 · Proposed COD March 2022
600 MW
Capacity
1
Components
Solar
10y 2m
In Queue
IA Executed
IA Phase
COD target: 2022
Total Duration
5y 10m
Schedule
52 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2022-03-31
Proposed project BPA-G0539 is a 600 MW solar generation project located in Crook County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an original queue entry date of May 16, 2016, and a proposed commercial operation date of March 31, 2022. The interconnection agreement (IA) for the project has been executed.
The project is composed of 600 MW of solar generation capacity. The point of interconnection (POI) is at the BPA Ponderosa Substation or on the interconnecting systems tying into the Ponderosa Substation. This development project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Deschutes
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
NRIS
Point of Interconnection
BPA Ponderosa Substation or on the interconnecting systems tying into the Ponderosa Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesTop solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.