BPA-G0513
20 MW generation in Morrow, OR · In queue since September 2015 · Proposed COD December 2016
20 MW
Capacity
1
Components
Solar
10y 10m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2016
Total Duration
1y 3m
Schedule
116 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2016-12-31
BPA-G0513 is a proposed solar generation project with a total capacity of 20 MW, located in Morrow County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of September 18, 2015. The proposed commercial operation date is December 31, 2016.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is on a 115 kV line tap proximate to Tower Road Switch Station.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
ERIS
Point of Interconnection
115 kV line tap proximate to Tower Road Switch Station
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project BPA-G0513Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.