BPA-G0501
1,100 MW generation in Klamath, OR · In queue since October 2014 · Proposed COD July 2018
1,100 MW
Capacity
1
Components
Gas
11y 9m
In Queue
Facility Study
IA Phase
COD target: 2018
Total Duration
3y 9m
Schedule
98 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2018-07-01
BPA-G0501 is a proposed generation project located in Klamath County, Oregon, with a total capacity of 1100 MW. The project, which utilizes gas-fired technology, is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of October 13, 2014. The proposed commercial operation date (COD) is July 1, 2018. The point of interconnection (POI) is the Captain Jack 500 kV Substation, and the project's interconnection status is currently in the Facility Study phase.
The development has been the subject of recent news coverage related to grid infrastructure. The project is composed of a single 1100 MW gas-fired component.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
—
Entity
BPA
Service Type
NRIS/ERIS
Point of Interconnection
Captain Jack 500 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-31