BHP-BHBE G7
200 MW generation in Campbell, SD · In queue since October 2007 · Proposed COD September 2010
200 MW
Capacity
1
Components
Wind
19y 1m
In Queue
IA Executed
IA Phase
COD target: 2010
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 11m
Schedule
198 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2010-09-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue data, date unknown
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: LBNL proposed COD of 2010-09-01 is 14+ years stale with no recent news or updates found. No current COD target available from research.
Developer: LBNL lists 'Third Planet Wind' as developer with no evidence of shell LLC structure or ownership changes. No recent news found to validate or update.
Status: LBNL shows 'active' with IA Executed, but 14-year gap between proposed COD (2010) and present with zero news coverage suggests project is dormant despite maintaining queue position.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
BHP-BHBE G7 is a proposed 200 MW wind generation project in Campbell County, South Dakota, in the western United States. The project is being developed by Third Planet Wind and consists of a single wind component with a capacity of 200 MW. It is planned to connect to the transmission system at the Pumpkin Buttes 230 kV point of interconnection, within the service territory of the utility Black Hills Power.
The project entered the Black Hills Power (BHP) interconnection queue on October 1, 2007, and holds an active status. It requested both Network Resource Interconnection Service (NRIS) and Energy Resource Interconnection Service (ERIS). The interconnection agreement for the project has been executed. The proposed commercial operation date was September 1, 2010, though the project remains listed as active in the queue well beyond that original target date.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
SD
County
Campbell
Grid Region
Mountain West
Market
—
Developer
Third Planet Wind
Utility
Black Hills Power
Entity
BHP
Service Type
NRIS/ERIS
Point of Interconnection
Pumpkin Buttes 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
FPL Energy Oliver Wind I LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.