Project BHP-BHBE G25 — Project Summary

Queue ID
BHP-BHBE G25
Capacity
115 MW
Technology
Gas
Status
active
Location
Pennington, SD
Region
West
Developer
Black Hills Power Inc.
IA Status
Cluster Study

BHP-BHBE G25

BHP-BHBE G25BetaActiveGasBHPLBNL

115 MW generation in Pennington, SD · In queue since June 2024 · Proposed COD June 2026

BA: WACMNERC: MRORC: SPP

115 MW

Capacity

1

Components

Gas

2y 5m

In Queue

Cluster Study

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

2 years

Schedule

6 months past proposed COD

Impact Study25%
Queue EntryJun 13, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-06

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Project statusUnder constructionKOTA Territory News · 2025-08-13

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Jun 6, 2026
From queue filing
Developer in saved assessment
Black Hills Power Inc.
From queue filing
Status at research time
Construction
Construction — groundbreaking occurred August 2025, on track for mid-2026 COD
Financing
Not recorded

Milestones in this assessment

GroundbreakingAug 2025

Groundbreaking ceremony held for Lange II gas plant in Rapid City area

kotatv.com
COD targetJun 6, 2026Latest in this assessment

Proposed commercial operation date per LBNL queue filing

Research sources and reasoning (1 recorded sources)

medium confidence at research time

  1. kotatv.com/2025/08/14/groundbreaking-new-power-plant-rapid-city/

Commercial operation date: LBNL queue filing shows proposed COD of 2026-06-06. No contradictory evidence from news sources, though news article from August 2025 describes groundbreaking, which is consistent with a mid-2026 target.

Developer: LBNL filing lists Black Hills Power Inc. as developer, which is the operating utility company (not a shell LLC). News source confirms this is a Black Hills Power project.

Status: LBNL shows 'active' queue status with Cluster Study phase. News extraction from August 2025 confirms 'under_construction' status with groundbreaking event, indicating project has advanced beyond queue filing.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The proposed project BHP-BHBE G25 is a 115 MW generation project located in Pennington County, South Dakota, in the West region. The project, developed by Black Hills Power Inc., utilizes an unspecified "Other" technology. It is interconnected to the Black Hills Power grid at the Lange Substation.

The project is currently in the Southwest Power Pool (SPP) interconnection queue, with an entry date of June 13, 2024. The proposed commercial operation date is June 6, 2026, and its interconnection agreement status is currently in the Cluster Study phase. This development project has been mentioned in recent news coverage related to grid infrastructure.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

SD

County

Pennington

Grid Region

Mountain West

Market

—

Developer

Black Hills Power Inc.

Utility

Black Hills Power

Entity

BHP

Service Type

NRIS

Point of Interconnection

Lange Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-05-31

View all articles

No Ask reports yet for this entity.

Ask about Project BHP-BHBE G25
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.