BHP-BHBE G2
100 MW generation in Campbell, SD · In queue since February 2001 · Proposed COD January 2010
100 MW
Capacity
1
Components
Coal
25y 9m
In Queue
IA Executed
IA Phase
COD target: 2010
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 11m
Schedule
206 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2010-01-06
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue data
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: LBNL proposed COD of 2010-01-06 is the only available date. Given this is a coal facility with queue date from 2001 and IA executed status, it likely came online around 2010 or earlier, but no independent verification exists.
Developer: LBNL lists 'Black Hills Generation' as developer. This appears to be the operating entity (subsidiary of Black Hills Energy/Corporation) rather than a project-specific shell LLC. No conflicting information available.
Status: LBNL shows 'IA Executed' status with 2010 proposed COD. For a coal facility queued in 2001, this timeline suggests it may have come online, but is_operational flag is false and no news confirms current status.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
BHP-BHBE G2 is a proposed 100 MW coal-fired generation project located in Campbell County, South Dakota, in the western region of the United States. The development project is being pursued by Black Hills Generation, with Black Hills Power serving as the associated utility. The project consists of a single coal generation component with a capacity of 100 MW.
The project is listed in the interconnection queue administered by Black Hills Power (BHP), which it entered on February 27, 2001. It proposes to interconnect at the Wyodak 230 kV point of interconnection and has requested Network Resource Interconnection Service (NRIS). The project's interconnection agreement has been executed, and its queue status remains active. The proposed commercial operation date was January 6, 2010.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
SD
County
Campbell
Grid Region
Mountain West
Market
—
Developer
Black Hills Generation
Utility
Black Hills Power
Entity
BHP
Service Type
NRIS
Point of Interconnection
Wyodak 230 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.