BHCT-BHCT G50
50 MW storage in Pueblo, CO · In queue since June 2024 · Proposed COD March 2026
50 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Cluster Study
IA Phase
COD target: 2026
Total Duration
1y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
BHCT-BHCT G50 is a proposed 50 MW battery storage project located in Pueblo County, Colorado. The project, under development by Black Hills Colorado Electric, LLC, consists of a single 50 MW battery component. It is interconnected within the West region and is in the Public Service Company of Colorado (PSCo) interconnection queue, with an entry date of June 12, 2024.
The proposed commercial operation date for the project is March 1, 2026. Its interconnection status is currently in the Cluster Study phase. The point of interconnection is at a substation, with approximate coordinates 38.3188659, -.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
Black Hills Colorado Electric, LLC
Utility
Black Hills Colorado Electric
Entity
BHCT
Service Type
NRIS
Point of Interconnection
a Substation, Approximate Coordinates: 38.3188659, -
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project BHCT-BHCT G50Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.