APS-Q596
330 MW generation in Yuma, AZ · In queue since May 2025 · Proposed COD August 2029
330 MW
Capacity
1
Components
Other
1y 6m
In Queue
Cluster Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-08-15
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Queue ID APS-Q596 is a proposed 330 MW generation project in Yuma County, Arizona, in the western United States. The project is listed under the "Other" technology category, with a single component of 330 MW, and no further detail on the generation type is provided. No developer name has been disclosed in the available queue data. The project would connect to the transmission system owned by Arizona Public Service (APS), at a point of interconnection on the North Gila–Hassayampa 500 kV transmission line, located at approximately 32.831681° N, 113.787946° W.
The project entered the APS interconnection queue on May 13, 2025, and is currently listed as active. It is in the Cluster Study phase of the interconnection process and has requested Network Resource Interconnection Service (NRIS). The proposed commercial operation date is August 15, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
NRIS
Point of Interconnection
North Gila - Hassayampa 500kV TL (32.831681°, - 113.787946°)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.