APS-Q573
200 MW generation in Pinal, AZ · In queue since May 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Other
2y 2m
In Queue
Cluster Study
IA Phase
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
APS-Q573 is a proposed 200 MW hybrid Solar+Battery project located in Pinal County, Arizona. The development project, consisting of 200 MW of solar capacity, is in the Arizona Public Service (APS) interconnection queue, under queue ID APS-Q573. The queue entry date is May 15, 2024, with a proposed commercial operation date of June 1, 2028. The project's interconnection agreement status is currently in the Cluster Study phase.
The point of interconnection is listed as 32.7339, -111.6359 at a tap on the Milligan to Casa Grande 230 kV line. The project is listed as active in the interconnection queue. The developer is listed as APS.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
NRIS
Point of Interconnection
tap on Milligan to Casa Grande 230 kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project APS-Q573Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.