APS-Q425
200 MW hybrid in Yuma, AZ · In queue since September 2021 · Proposed COD December 2024
200 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Cluster Study
IA Phase
COD target: 2024
Total Duration
3y 3m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
APS-Q425 is a proposed 200 MW hybrid solar and battery project located in Yuma County, Arizona. The project, under development by Arizona Public Service (APS), consists of 200 MW of solar capacity. It is listed in the Arizona Public Service interconnection queue (APS-Q425) with an entry date of September 30, 2021, and a proposed commercial operation date of December 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The point of interconnection for APS-Q425 is the Orchard 230kV substation. This proposed project has appeared in recent news coverage regarding renewable energy development in the southwestern United States.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
ERIS
Point of Interconnection
Orchard 230kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project APS-Q425Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.