APS-Q362
275 MW hybrid in Pinal, NC · In queue since September 2020 · Proposed COD October 2023
275 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Cluster Study
IA Phase
COD target: 2023
Total Duration
3y 1m
Schedule
34 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-01
APS-Q362 is a proposed 275 MW solar and battery hybrid project located in Pinal County, Arizona. The development project consists of 275 MW of solar generation capacity. It is listed in the Arizona Public Service interconnection queue (APS-Q) with a queue entry date of September 30, 2020, and a proposed commercial operation date of October 1, 2023. The project's interconnection status is currently in the System Impact Study phase.
The point of interconnection for the proposed project is the Milligan - Casa Grande 230kV substation. The project is located in the Western region of the United States. Recent news coverage has discussed the project's potential impact on the local energy grid.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
NRIS/ERIS
Point of Interconnection
Milligan - Casa Grande 230kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project APS-Q362Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.