APS-Q348
300 MW hybrid in Coconino, AZ · In queue since September 2020 · Proposed COD December 2024
300 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Cluster Study
IA Phase
COD target: 2024
Total Duration
4y 3m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
APS-Q348 is a proposed 300 MW hybrid solar and battery energy storage project located in Coconino County, Arizona. The project, interconnected with Arizona Public Service (APS), entered the APS interconnection queue on September 22, 2020, with a proposed commercial operation date of December 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The project consists of 300 MW of solar generation capacity. It is located in the western United States and interconnects at the Moenkopi El Dorado 500kV Line. The project has appeared in recent news coverage regarding renewable energy development in Arizona.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
NRIS/ERIS
Point of Interconnection
Moenkopi El Dorado 500kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project APS-Q348Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.