APS-Q319
1,000 MW generation in San Juan, NM · In queue since September 2019 · Proposed COD September 2026
1,000 MW
Capacity
1
Components
Wind
7y 2m
In Queue
Suspended
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
APS-Q319 is a proposed 1,000 MW wind generation development project located in San Juan County, New Mexico, in the western United States. The project's developer is not identified in the available data. The project has been submitted to the interconnection queue administered by Arizona Public Service (APS), and it would connect to the grid at the Four Corners 345 kV point of interconnection. It has requested Network Resource Interconnection Service (NRIS).
The project entered the APS interconnection queue on September 30, 2019, and had a proposed commercial operation date of September 30, 2026. Its queue status is listed as suspended, and its interconnection agreement status is likewise reported as suspended. The project consists of a single wind component with a capacity of 1,000 MW and does not include battery storage or other hybrid elements.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
NRIS
Point of Interconnection
Four Corners 345kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wind queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.