APS-Q310
450 MW hybrid in Yuma, AZ · In queue since August 2019 · Proposed COD May 2023
450 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Phase
COD target: 2023
Total Duration
3y 9m
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2023-05-31
The proposed APS-Q310 project is a 450 MW solar and battery hybrid development located in Yuma County, Arizona. The project consists of 450 MW of solar generation. It is interconnected to the Arizona Public Service (APS) grid at the Hoodoo Wash 500kV point of interconnection.
The project is listed in the APS interconnection queue with an entry date of August 28, 2019, and a proposed commercial operation date of May 31, 2023. The interconnection agreement (IA) for the project has been executed. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
NRIS/ERIS
Point of Interconnection
Hoodoo Wash 500kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.