437.9 MW Conventional Hydroelectric (26 MW) + Hydroelectric Pumped Storage (412 MW) operating in Warren, PA
437.9 MW
Nameplate Capacity
3
Generators
units
Hybrid (2)
Technology
Conventional Hydroelectric + Hydroelectric Pumped Storage
1970
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
41.8389, -79.0056
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
County
Warren, PA
Nearby Plants
The starting substation is nearby, but its connection to this plant is unconfirmed.
3 mapped line sections connect the two facilities over 18.497 km. The line reaches both facility footprints in the source data.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Owner data does not fully agree across sources.
Sources can describe different roles or reporting dates. The source-specific values below are retained for comparison.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Seneca Generation LLC | Seneca Generation | — |
| Owner(s) | Seneca Generation LLC | LS Power Development | — |
| Status | Operating | operating | — |
The Seneca Pumped Storage Generating Station is a hydroelectric power plant using pumped storage of water to generate electric power. It is located near Warren, Pennsylvania in Warren County.
Read more on WikipediaSummary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Seneca Generation LLC, located in Warren County, Pennsylvania, is a 437.9 MW hybrid hydroelectric and pumped storage facility. The plant, which began operating in 1970, utilizes water as its primary fuel source. It is owned by LS Power Development and operated by Seneca Generation LLC. The facility consists of three generators employing conventional hydroelectric and pumped storage technologies.
Seneca Generation LLC operates within the PJM Interconnection, LLC balancing authority and the RFC NERC region. It is ranked as the second largest of four hydroelectric plants in Pennsylvania and the 54th largest of 194 hydroelectric plants nationally.
ISO/RTO
PJM
Market
ISO/RTO Member
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC (PJM)
Grid Voltage
230.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−27.7K MWh
Net Charging
-353.3K MWh
Annual Net Energy
-9.2%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $1.0B
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Glade Substation · 230 kV
Substation Distance
< 10 km
Operator
Penelec
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
SENECA 13KV GEN1
Pricing Hub
WESTERN HUB
Node Source
EIA-860 direct report
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all articlesSeneca Generation LLC
Data-driven briefing on Seneca Generation LLC — fleet, generation, financial, and news signals.
SMUD at Van Conett
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Hydro Plant
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.