4.6 MW Solar operating in Pulaski, AR
4.6 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2023
Operating Since
Coordinates
34.6991, -92.2118
County
Pulaski, AR
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Today's Power, Inc. | Today's Power, Inc. | — |
| Owner(s) | Today's Power, Inc. | Today's Power, Inc. | — |
| Status | Operating | operating | — |
GEM identifies the owner as Today's Power, Inc.
This entity is not yet in the GEM ownership database — chain unavailable.
The Zeuber solar photovoltaic plant is located in Pulaski County, Arkansas. It is owned and operated by Today's Power, Inc. The plant began operating in 2023 and has a total capacity of 4.6 MW from a single generator. Zeuber ranks 39th out of 77 power plants in Arkansas and 3238th out of 7108 plants nationally.
The plant utilizes single-axis tracking to maximize solar energy capture. In its latest year of operation, Zeuber generated 7,302 MWh of electricity, resulting in a capacity factor of 18.1%. The plant operates within the Midcontinent Independent Transmission System Operator (MISO) balancing authority and is located in the SERC NERC region.
Generated from EIA, GEM, and public data sources
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
SERC — SERC Reliability Corporation
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Grid Voltage
12.47 kV
Regulatory Status
RE — Regulated
Entity Type
Cooperative
Sector
Electric Utility
Historic generation and capacity factor for this asset — the foundation for forward forecasts on the InfraSure platform.
338 MWh
Latest Month
7.3K MWh
Annual Generation
18.1%
Capacity Factor
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$1,543/kW
Est. Construction Cost
Total estimated cost: $7.1M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
LR Port Substation · 115 kV
Substation Distance
< 10 km
Operator
Entergy Arkansas
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
ARKANSAS.HUB
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about ZeuberForward forecasts, scenario decomposition, and risk-decision tooling for this asset.