113 MW BESS operating in Yuma, AZ
113 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
2025
Operating Since
Coordinates
32.9942, -113.5098
County
Yuma, AZ
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Leeward Asset Management, LLC | — | — |
| Owner(s) | Leeward Asset Management, LLC | — | — |
| Status | Operating | — | — |
Sierra Pinta BESS is a battery energy storage system located in Yuma County, Arizona. The plant has a total capacity of 113 MW and consists of a single generator. It is owned and operated by Leeward Asset Management, LLC. The plant's primary fuel is electricity (MWH), which it uses to charge and discharge its batteries.
Sierra Pinta BESS operates within the Arizona Public Service Company balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. According to state rankings, the plant is the 46th largest out of 47 plants in Arizona. Nationally, it is ranked 453 out of 514 plants.
Generated from EIA, GEM, and public data sources
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
Arizona Public Service Company (AZPS)
Grid Voltage
500.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−2.1K MWh
Net Charging
—
Annual Net Energy
—
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$1,361/kW
Est. Construction Cost
Total estimated cost: $153.8M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this asset.