Search plants, projects, owners, and states
200 MW BESS operating in Maricopa, AZ
200 MW
Nameplate Capacity
2
Generators
units
Batteries
Technology
2024
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
33.7131, -112.3242
Reference point reported to EIA.
County
Maricopa, AZ
Nearby Plants
The route starts at a transmission substation on the mapped site; its link to the plant’s generation equipment is unconfirmed.
1 mapped line section connects the two facilities over 0.173 km. The line reaches both facility footprints in the source data.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Reverse views of the same physical route are grouped in the route selector. All source records are retained.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | AES Clean Energy | — | — |
| Owner(s) | AES Clean Energy | — | — |
| Status | Operating | — | — |
Summary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Westwing is a 200 MW battery energy storage system (BESS) located in Maricopa County, Arizona. The plant began operating in 2024 and is owned and operated by AES Clean Energy. The facility utilizes batteries as its primary fuel source (designated as 'MWH' in some datasets) and consists of two generators. The BESS has a duration of 4.08 hours.
Westwing operates within the Arizona Public Service Company balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. It is ranked as the 37th largest power plant out of 47 in Arizona, and 299th nationally out of 514. The plant's operation has been noted in at least two news articles, both of which focus on grid-related aspects.
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
Arizona Public Service Company (AZPS)
Grid Voltage
230.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−2.2K MWh
Net Charging
-21.7K MWh
Annual Net Energy
-1.2%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$1,361/kW
Est. Construction Cost
Total estimated cost: $272.2M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-14
View all articlesBattery Storage queue pipeline by status
Data tables and metrics from the InfraSure database.
Battery storage queue pipeline
Summary analysis with parallel narrative sections and visualizations.
Battery Storage queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Westwing
Data-driven briefing on Westwing — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this asset.