102.6 MW BESS operating in Maverick, TX
102.6 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
2025
Operating Since
Coordinates
28.6995, -100.4035
County
Maverick, TX
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Fort Duncan BESS, LLC | — | — |
| Owner(s) | Fort Duncan BESS, LLC | — | — |
| Status | Operating | — | — |
Fort Duncan BESS is a 102.6 MW battery energy storage system located in Maverick County, Texas. The plant began operating in 2025 and has one generator. It is owned and operated by Fort Duncan BESS, LLC. The facility utilizes batteries as its primary fuel source, categorized as MWH in energy data.
The plant operates within the Electric Reliability Council of Texas (ERCOT) balancing authority and the TRE NERC region. Fort Duncan BESS has a storage duration of 2 hours. According to available rankings, the plant is the 194th largest in Texas out of 224 plants and the 472nd largest nationally out of 514 plants.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
138.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−1.7K MWh
Net Charging
-10.4K MWh
Annual Net Energy
-2.0%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$1,361/kW
Est. Construction Cost
Total estimated cost: $139.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
ERCOT
LMP Node
FTDUNCAN_RN
Pricing Hub
HB_SOUTH
Alt. Hub / Zone
LZ_SOUTH
Location Type
Resource Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Fort Duncan BESSForward forecasts, scenario decomposition, and risk-decision tooling for this asset.