200 MW Solar operating in Emery, UT
200 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2025
Operating Since
Coordinates
39.1824, -110.9772
County
Emery, UT
Nearby Plants
Forward-looking, asset-specific exposure profile combining climate hazards, generation variability, and counterparty risk into a single decision-grade signal.
See the full risk decomposition + scenarios for this asset.
Request a demo →| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Hornshadow Solar II, LLC | Hornshadow Solar II LLC | — |
| Owner(s) | Hornshadow Solar II, LLC | Hornshadow Solar II LLC | — |
| Status | Operating | operating | — |
GEM identifies the owner as Hornshadow Solar II LLC
This entity is not yet in the GEM ownership database — chain unavailable.
Hornshadow Solar II, LLC is a 200 MW solar photovoltaic power plant located in Emery County, Utah. The plant, owned and operated by Hornshadow Solar II, LLC, commenced operations in 2025. It utilizes a single generator and fixed-tilt solar tracking technology. The plant is interconnected to the grid within the PacifiCorp - East balancing authority, which falls under the Western Electricity Coordinating Council (WECC) NERC region.
In its latest year of operation, Hornshadow Solar II generated 227,612 MWh of electricity, achieving a capacity factor of 25.7%. The plant ranks as the 4th largest solar facility out of 7 in the state of Utah, and it holds the 230th position nationally among 639 solar plants. Recent news coverage indicates grid-related developments concerning the plant.
Generated from EIA, GEM, and public data sources
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
PacifiCorp - East (PACE)
Grid Voltage
245.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
20.4K MWh
Latest Month
227.6K MWh
Annual Generation
25.7%
Capacity Factor
2023
$1,544/kW
Est. Construction Cost
Total estimated cost: $308.8M
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
Last updated 2026-03-26
View all articlesTop solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.