185 MW BESS operating in Yuma, AZ
185 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
2025
Operating Since
Coordinates
32.9460, -113.4916
County
Yuma, AZ
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | AES Clean Energy | — | — |
| Owner(s) | AES Clean Energy | — | — |
| Status | Operating | — | — |
McFarland C is a battery energy storage system (BESS) located in Yuma County, Arizona. The plant has a total capacity of 185 MW and consists of a single generator. It began operating in 2025 and is owned and operated by AES Clean Energy. The BESS has a duration of 4 hours.
The plant's primary fuel source is listed as MWH, indicating it draws power from the grid to charge its batteries. McFarland C operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. In terms of size, McFarland C ranks as the 38th largest power plant in Arizona out of 47, and 339th nationally out of 514.
Generated from EIA, GEM, and public data sources
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
California Independent System Operator (CISO)
Grid Voltage
500.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−1.6K MWh
Net Charging
-12.0K MWh
Annual Net Energy
-1.1%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2023
$1,361/kW
Est. Construction Cost
Total estimated cost: $251.8M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
CAISO
LMP Node
HN_LNODER2A
Pricing Hub
TH_SP15_GEN-APND
Location Type
Pricing Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about McFarland CForward forecasts, scenario decomposition, and risk-decision tooling for this asset.