400 MW Batteries (200 MW) + Solar Photovoltaic (200 MW) planned in Matagorda, TX
400 MW
Nameplate Capacity
2
Generators
units
Hybrid (2)
Technology
Batteries + Solar Photovoltaic
Planned: —
Planned Operation
Coordinates
28.8660, -96.1217
County
Matagorda, TX
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
Request a demo →Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Eldora Energy LLC | Eldora Energy | — |
| Owner(s) | Eldora Energy LLC | Advanced Power | — |
| Status | Planned | announced | — |
Eldora Energy LLC is a 400 MW hybrid power plant located in Matagorda County, Texas. The plant, owned and operated by Eldora Energy LLC, a subsidiary of the Swiss company Advanced Power, utilizes both battery storage and solar photovoltaic technologies. It consists of two generators and is fueled by MWH (presumably electricity from the grid, given the battery component). The solar array uses a fixed tilt tracking system.
Eldora Energy LLC operates within the Electric Reliability Council of Texas, Inc. (ERCOT) balancing authority and the TRE NERC region. It is ranked as the 29th largest power plant in Texas out of 224, and 99th nationally out of 514. The plant's hybrid nature and location in the ERCOT market have garnered some industry attention, as evidenced by two news articles, one focusing on deals and the other on general industry news.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
Electric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
345.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
No generation data available for this plant.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
Request a demo →2023
$1,361/kW
Est. Construction Cost
Total estimated cost: $544.4M
Point of Interconnection
Nearest Substation
South Texas Project Tap · 138 kV
Substation Distance
< 10 km
Operator
American Electric Power
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ERCOT
LMP Node
—
Pricing Hub
HB_HOUSTON
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.
Last updated 2026-03-26
View all articlesTop solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the InfraSure database.