Search plants, projects, owners, and states
5 MW BESS operating in Sutter, CA
5 MW
Nameplate Capacity
2
Generators
units
Batteries
Technology
2022
Operating Since
Coordinates
39.1713, -121.6621
County
Sutter, CA
Nearby Plants
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | VESI 10 LLC | — | — |
| Owner(s) | VESI 10 LLC | — | — |
| Status | Operating | — | — |
Tierra Buena Energy Storage is a 5 MW battery energy storage system located in Sutter County, California. The plant began operating in 2022 and is owned and operated by VESI 10 LLC. It consists of two generators utilizing battery technology, with a total storage capacity of 2.5 MWh. The battery chemistry is lithium-ion (LIB), providing a storage duration of 1 hour.
The facility operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. Tierra Buena Energy Storage is ranked as the 227th largest power plant in California out of 300, and 990th nationally out of 1205 facilities. The plant's primary fuel source is electricity (MWH), indicating it charges from the grid and discharges during periods of high demand or grid instability.
Generated from EIA, GEM, and public data sources
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
California Independent System Operator (CISO)
Grid Voltage
12.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−86 MWh
Net Charging
-917 MWh
Annual Net Energy
-2.1%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2022
$1,205/kW
Est. Construction Cost
Total estimated cost: $6.0M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Point of Interconnection
Nearest Substation
Pease Substation · 115 kV
Substation Distance
0.155 km
Operator
Pacific Gas and Electric Company
Coord Source
OSM spatial
Market Position
ISO/RTO Market
CAISO
LMP Node
PEASE_1_N009
Pricing Hub
TH_NP15_GEN-APND
Location Type
Pricing Node
Node Source
Curated node match
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
No insights linked yet for this plant.
Insights enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No Ask reports yet for this entity.
Ask about Tierra Buena Energy StorageForward forecasts, scenario decomposition, and risk-decision tooling for this asset.