Search plants, projects, owners, and states
100 MW BESS operating in Kern, CA
100 MW
Nameplate Capacity
1
Generators
unit
Batteries
Technology
2021
Operating Since
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Plant reference point
35.0288, -118.1392
Reference point calculated from the selected footprint.
Mapped site outline
Site outline mapped in OpenStreetMap. It is not a surveyed or legal boundary.
County
Kern, CA
Nearby Plants
The starting substation is nearby, but its connection to this plant is unconfirmed.
3 mapped line sections connect the two facilities over 1.014 km. At least one endpoint uses a nearby spatial match.
The actual electrical circuit, the official point of interconnection (POI), and the market settlement node require separate evidence.
Source checked 26 Oct 2026. Facility colors and shapes indicate source-reported function, not ownership or a confirmed plant connection.
This release uses a national source capture. Coverage and electrical detail vary by location; missing map data does not mean there is no connection. Lettered substation names are display labels where the source has no name. They do not identify ownership or function.
Source snapshot: 25 Oct 2026.
Reverse views of the same physical route are grouped in the route selector. All source records are retained.
Method: source-node-path-v2 · Release: gcr-73c6ce9c596ada3ec63d5523
Forward-looking, asset-specific exposure analytics combining climate hazards, generation variability, and counterparty risk into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this asset.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Terra-Gen Operating Co-BESS | — | — |
| Owner(s) | Terra-Gen Operating Co-BESS | — | — |
| Status | Operating | — | — |
Summary generated Mar 21, 2026 (UTC).
Source dates used by this summary were not recorded.
These may postdate the saved summary; they do not establish which inputs it used.
Sanborn BESS 1 is a 100 MW battery energy storage system located in Kern County, California. The plant began operating in 2021 and has one generator. It is owned and operated by Terra-Gen Operating Co-BESS. The facility utilizes lithium-ion batteries (LIB) to provide 200 MWh of energy storage, equating to a storage duration of 2 hours. The plant's primary fuel is listed as MWH, indicating it draws power from the grid to charge its batteries.
Sanborn BESS 1 operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. As of the latest rankings, it is the 110th largest power plant in California out of 112, and the 484th largest in the United States out of 514.
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
California Independent System Operator (CISO)
Grid Voltage
230.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
Connection evidence
Mapped route candidate
Monthly net generation as reported to EIA-923 — useful for historical context. Confidence varies sharply by fuel type; the band above and the “About this data” button explain the caveats specific to this plant and how InfraSure’s in-house model handles them.
−1.3K MWh
Net Charging
-16.2K MWh
Annual Net Energy
-1.8%
Capacity Factor
Positive values indicate net discharge (generation exceeds station load). Negative values indicate net charging. Pure battery storage plants are typically net negative due to round-trip efficiency losses.
Forward-looking generation outlook with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this asset.
2021
$1,796/kW
Est. Construction Cost
Total estimated cost: $179.6M
Forward revenue, DSCR bands, and refinancing risk projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this asset.
Market Position
ISO/RTO Market
CAISO
LMP Node
—
Pricing Hub
TH_SP15_GEN-APND
Node Source
Shared substation inference
No wholesale contracts disclosed in FERC EQR for this plant.
FERC EQR captures bilateral wholesale energy + capacity contracts ≥$1M/yr filed quarterly by jurisdictional sellers — covers renewable PPAs, thermal energy sales agreements, capacity contracts, and tolling agreements alike. Many plants don't appear: regulated-utility output flows to ratepayers via cost-of-service rather than bilateral contracts; small projects fall below the filing threshold; tax-equity-financed renewables route offtake to investors not utilities; merchant plants sell into ISO clearing markets without bilateral contracts. News-extracted buyer facts (below) may surface contracts disclosed only through announcements.
Last updated 2026-03-26
View all 6 articlesForward forecasts, scenario decomposition, and risk-decision tooling for this asset.